Manufacturer Elkem
Array Rating 5.5kW
PV Technology poly-Si
Array Structure Fixed: Ground Mount
Installed 2014

View on Map    Graphs    Download Data

Current Output

Array Rating 5.5kW
Panel Rating 250W
Number Of Panels 22
Array Area 36.30 m²
Type Of Tracker N/A
Inverter Size / Type SMC 6000A
Installation Completed Tue, 9 Dec 2014
Array Tilt/Azimuth Tilt = 20, Azi = 0 (Solar North)


Notes on the Data

  1. Metering failure

    Circuit breaker supplying the metering equipment for sites 23-38 tripped off on Aug 19th and was discovered and turned back on on Aug 23rd. This resulted in a lack of generation data for these sites during this time but did not stop the sites from physically generating.


    Thu, 19 Aug 2021

  2. System Disconnection for Cabling Works

    All arrays at the Solar Centre were disconnected from approximately 2.00pm to 3.00pm on Monday, 9 July 2018 in preparation for the cable between the main switchboard and distribution board being upgraded. Array sites #23-38 remained disconnected while the main feeder cable to these sites was replaced in subsequent days, but all systems were re-connected by early afternoon on Thursday, 12 July 2018.


    Mon, 9 Jul 2018

  3. System Outage at Australia Day Long Weekend

    A breaker tripped at around 12.30pm on Friday, 26 January, likely due to high generation levels reached at this peak time on this high irradiance day. Connection was restored after the Australia Day long weekend at around 11.30am on Monday, 29 January but shortly tripped again.

    UPDATE 26-02-2018. The cause of this reoccurring issue has been identified and will be rectified. The solution requires the upgrading of a key distribution cable. This should be completed in the coming months.


    Fri, 26 Jan 2018

  4. Connection Restored After Christmas/NY Period

    Arrays have been re-connected following the outage that disconnected multiple sites from Christmas day 2017. The outage is believed to have been triggered by the tripping of two circuit breakers in separate distribution boards, making the diagnosis initially elusive. The ability of the common circuit shared by these arrays to keep abreast with increasingly high current demands as new arrays are installed and generation conditions are high is presently being addressed. For the same reason, intermittent outages persisted in the summer of early 2018.


    Fri, 19 Jan 2018

  5. System Outage at Christmas/NY Period

    A system outage was caused by a circuit breaker trip at approximately 2pm on a high generation day shortly after installation of a new array at the DKA Solar Centre. The outage commenced on 25 December continuing into the new year and is being addressed.


    Mon, 25 Dec 2017

  6. System Outage for New Array Connection

    Sites 23 through to 37 experienced an outage today from 11:10 to 11:50. The outage was due to the local distribution board being temporarily being taken offline to allow for the connection of a new PV system.  


    Wed, 20 Dec 2017

  7. Monitoring Interruption for UPS Battery Replacement

    The disconnection and re-connection of the solar arrays and weather station equipment while a new site connection was being established prompted the already flattening UPS batteries which power the site’s energy meters to fail and require immediate replacement. Data recording was affected from approximately 2.30pm ACST, Monday 10 July to 4.00pm, Wednesday 12 July.

    Affects weather data for DKASC, Alice Springs


    Wed, 12 Jul 2017

  8. Partial System Outage

    One of the major switchboards at the DKASC lost power yesterday 01/12/2016 at ~11:00 am. This isolated and shutdown array sites 23 through to 37 inclusive. The switchboard was re-energised at ~16:30 today (02/12/2016) and is again operating normally. Data for this period for these sites is lost.


    Fri, 2 Dec 2016

  9. Site 35: Temporary Shutdown

    Site 35 was temporarily shutdown on the 11th May 2016 from ~ 10:00 am to 6:00 pm. This was to de-energize the underground cable feeding the site to allow for safe trenching and augering work on neighbouring sites.


    Wed, 11 May 2016

  10. System Outage - Sites 4, 5, 17, 20, 22, 34 and 35

    On the 5th June 2015, A Friday before a long weekend, seven individual PV systems at the DKASC were switched off by unknown persons and for unknown reasons. The outage was not noted until the following Tuesday when O&M staff returned to work and found the main circuit breakers for sites 4, 5, 17, 20, 22, 34 & 35. turned off. These systems were all turned back on again on the 9th March when the problem was detected.


    Wed, 10 Jun 2015



>  Answer to Spotlight Question

Onsite at the DKA Solar Centre in Alice Springs are a series of quiz-like Spotlight Questions at each array. Visit the centre and scan the QR code at each sign to test your knowledge – and check your answer here!

Q: If you own a solar PV system, how do you keep tabs on its status and performance?

A: Many solar inverters come with their own proprietary monitoring software which allows users to remotely track performance of their solar PV system, online and often on their personal device. These generally have basic capabilities, and more advanced logging products may be purchased from the same or other manufacturers. PV systems also have a main energy meter that can record the total energy exported by the system. Depending on the meter's capabilities and ownership (often the electricity retailer or network operator), this can also avail high resolution data, as can temporary loggers installed by qualified personnel. In general, an ongoing awareness of the expected performance of a system may be borne in mind when checking one's electricity bills; a general rule of thumb is 1 kW of installed PV capacity producing 4-5 kWh energy per day in sunny conditions (location-dependent) so knowing one's electricity rates ($/kWh) can allow users to roughly calculate the expected savings on each electricity bill. Such forecasts may be provided by the system installer.